Footing is done, column is placed but not filled, I measured the boundaries, there is a shift of one feet in all the columns because the boundary was measured one feet wrong by the contractor what can i do now
Adjust the Structural Design – Consult Your Structural Engineer immediately.
Depending on the design, it may be possible to modify the beam layout to accommodate the column shift without compromising the structure’s integrity.