Awarded as the best online publication by CIDC

Tunneling

Submerged Floating Tunnel

By
Prof. Amol B. Kawade, Miss.Shruti P. Meghe
Amrutvahini College of Engineering, Sangamner

Abstract
Several crossings with a variety of different conditions under which a Submerged Floating Tunnel, SFT or Archimedes Bridge, may be used. However, swell, vortex shedding and slowly varying internal waves due to layers of different salinity presented a hazard of significant dynamic oscillations. In addition to the challenge of these various conditions some common accidental situations have to be solved for all applications including fire, sinking ships, falling anchors as well as sudden massive water ingress into the tube. Combining with the characteristics of submerged floating tunnel (SFT) and surrounding environment, it is of great theoretical and practical significance to develop research in the areas of potential risk and impact factors, risk index system, risk level of SFT. Risk management workflow of SFT was given. Then we focused on discussing the potential risks of SFT in investment, design, and environmental condition during planning and feasibility study stage.
Read More

What is the difference between cut-and-cover method and cover-and-cut method in tunnel construction?

“Cut-and-cover” method involves the construction of open cut at the first place, followed by the construction of tunnels under open excavation. Upon completion of the structure, backfilling and reinstatement would be subsequently carried out.

Advertisements

“Cover-and-cut” method involves firstly the construction of cover followed by the second stage in which construction activities are carried out under the cover. As such, the disturbance to the public owing to constructional activities could be reduced to a minimum.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

How could ground freezing stop ingress of groundwater in excavation?

The concept of ground freezing involves the lowering of temperature of ground near the excavation area. Drillholes with designed spacing are installed so that a chilled brine or liquid nitrogen is introduced into the holes. Brine requires continuous circulation while liquid nitrogen is for rapid freezing and it is unrecoverable. With the addition of a chilled brine or liquid nitrogen, the groundwater is frozen into ice. Upon frozen, soils exhibit higher shear strength and the frozen zone acts as an impermeable barrier so that water could not enter the excavation zone.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

What are the differences in design between normal precast concrete pipes and pipes used for pipe jacking?

For pipes used for pipe jacking, they should possess the following characteristics:

(i) Pipes should have high concrete strength to withstand the stress induced during the jacking process.

(ii) There is tight tolerance in pipe dimension and the pipe joints are specially designed to provide trouble-free joint details. Two commonly available joints are rebated joint and butt end joint.

Advertisements

(iii) Pipes preferably should have smooth external concrete finishes to reduce the friction between the pipes and surrounding soil.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

In the design of pipe jacking, what particular areas on pipe joints should engineers take care of?

Since in pipe jacking, the jacked pipes could hardly be jacked in the designed level and alignment and some deviation from the original one is commonly acceptable provided that the deviation are within the tolerance of the Contract. However, in order to avoid damage made to the pipe joints due to overstressing, it is necessary to estimate the stress concentrations resulting from these angular deflections.

Advertisements

Note: Pipe jacking is a trenchless method in which pipes are jacked underground from jacking pits and receiving pits.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

How can lubricants reduce the jacking forces?

The lubricating fluid serves to reduce the jacking force in the following ways:

(i) It saturates the overcut leading to partial and complete buoyancy of the jacking pipe in the cavity. As such, the contact surface area between the jacking pipe and soils is decreased.

(ii) It stabilizes the cavity by limiting the radial effective stress acting on the jacking pipe.

Advertisements

(iii) The interface friction angle between the soils and the jacking pipe are reduced by the lubricants.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

In pipe jacking, can engineers roughly estimate the order of stress concentration in pipe joints?

Theoretical line and level of pipelines can hardly be achieved in pipe jacking. As such, the provision of angular deflection is made at pipe joints to accommodate such deviation. Normally, maximum allowable angular deflection at pipe joints in pipe jacking is 0.5o.

Advertisements

As a rule of thumb, the stress concentration at a pipe joint is about 3 times the joint stress resulting from uniform distribution of stress. As such, for grade 50MPa precast concrete pipe, the allowable uniform joint stress is expected to be one-third of its compressive strength, i.e. 16.67MPa.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Can pipe jacking be implemented in a fast manner?

Energy is a function of load and speed. Damage may occur on the jacking pipes if it is incapable of absorbing the energy. Pipe jacking requires large energy in the process. Jacking pipes are low speed energy absorbers. To cater for the low-speed-energy absorbing characteristics of jacking pipes, hydraulic jacks should be designed to provide high loads with low speeds.

Advertisements

Otherwise the excessive high speed generated by hydraulic jacks would cause kinetic damage to the pipes.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

What is the difference between NATM and Sprayed Concrete Lining?

The New Austrian Tunneling Method originated from rock tunnels and it requires the use of rockbolts and shotcrete swiftly after blasting. Institution of Civil Engineers has renamed it as Sprayed Concrete Lining for construction of tunneling linings by this method in soft ground.

Advertisements

There are some distinct differences in design philosophy between NATM and Sprayed Concrete Lining. In fact, it is not practical to mobilize inherent soil strength through deformation in soft ground. For lower strength of soils in soft ground, there should not be any delay in completing primary support and ground deformation should be reduced as much as possible.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Is NATM a tunneling method or a tunneling concept?

In the original version of the New Austrian Tunneling Method, it is a tunneling concept with a set of main principles as follows:

(i) Application of thin-spayed concrete lining

(ii) Closure at invert to form a complete ring as soon as possible

(iii) Measurement of deformation until equilibrium is attained

Advertisements

It is a design concept in which the ground (soil or rock) enclosing the opening becomes a load-bearing element through formation of ring-like body. It uses all available means to develop maximum self-supporting capacity to provide support of the underground opening. In essence, it makes use of geological stress of surrounding soils to stabilize the opening. Therefore, NATM is a tunneling philosophy and concept rather than excavation techniques.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Ask a question