Awarded as the best online publication by CIDC

Tunneling

Why does pipejacking machine usually get stuck when the ground condition change from soil to very hard rock?

When the pipejacking machine moves from a region of soil to very hard rock, it will be subject to damage of cutting disc. To break and loosen the rock, the pipejacking machine applies a large torque on cutting wheels.

However, with the change of soft region to hard region, the pipejacking machine is still under the same jacking load. As such, this results in insufficient or little space for the movement of the machine against the rock face, leading to damage and exhaustion of the pipejacking machine.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Why does the problem ground settlement occur when pipe-jacking machine enters mixed ground with soils and boulders?

The rate of cutting through soils is faster than that of cutting through boulders for pipe-jacking machine. As such, when pipe-jacking machine enters a region of mixed ground with soils and boulders, the machine has the tendency to move towards the direction of soft soils because of the difference of rate of advancement of pipe-jacking machine for soils and boulders. Consequently, migration of soft soils occur which contributes to ground settlement. The degree of settlement is dependent of the depth of soil cover, soil property and the size of boulders.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Why are intermediate jacks designed in some pipe jacking projects?

When the process of pipe jacking stops, building up of resistance is very fast in some soil. For instance, increase in jacking force of 20%-40% is required for a stoppage of pipe jacking for just several hours. Hence, it is recommended that pipe jacking should be carried out in a continuous operation.

Advertisements

For a long pipeline, the frictional forces established between the jacking pipes and soil is high. Sometimes, such resisting forces may be so high that they can hardly be overcome by the jacks in jacking pits. Moreover, even if the jacks can overcome the high frictional forces induced during jacking, high loads are experienced in jacking pipes during driving. Jacking pipe’s material e.g. concrete may not have sufficient strength to resist these stresses and hence pipe strength is another factor that governs the need for consideration of using intermediate jacks.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

In precast concrete jacking pipes, sometimes grout holes are designed inside these precast pipes. Why?

Grout holes are present in precast jacking pipes for the following reasons:

(i) They serve as the locations for injection of bentonite or other lubricant. Lubricant is used for both granular soils and cohesive soils to trim down the frictional resistance. For cohesive soils, the soils cannot get onto the pipes by the presence of lubricant and the shearing plane lies within the lubricant as suggested by R. N. Craig (1983). On the other hand, for granular soils, the lubricant mixes with soils with a significantly reduced friction. With the use of lubricant, longer pipe lengths can be jacked without the use of intermediate jacking station.

Advertisements

(ii) They provide the inlet locations for subsequent grouting works after completion of pipe jacking to fill completely the void space between the pipes and surrounding soils.

(iii) They are used as lifting holes when placing the precast jacking pipes into rails inside the jacking pits.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Packers are normally introduced in pipe joints in pipe jacking. Why should packers be kept 20mm back from the edge of concrete?

Joint stress is induced in pipe joints during pipe jacking. Packers are normally installed in pipe joints to avoid localized stressing of joints leading to concrete crushing. In essence, packers should be elastic enough to take the reloading jacking force. Moreover, it should be thick enough to take the compression of maximum joint stress. Theoretically speaking, packers should be provided in all of the joint area except 20 mm back from the edge of concrete. The reason of such provision is to reduce the risk of local spalling of side edges.

packer in pipe joint

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Is thrust wall an essential element in pipe jacking? Can it be omitted if there is insufficient depth for constructing normal thrust wall?

Thrust wall is an essential element in pipe jacking and it provides the reaction against the pipe jacking operation. In poor ground, consideration may be given to using piling or other methods to increase the stiffness of thrust wall. When there is insufficient depth to construct thrust wall (e.g. jacking through an embankment), a structure has still be constructed to provide the reaction to pipe jacking. In this case, the resistance to horizontal jacking loads is resisted by piles, ground anchors or other methods to reinforce the structure.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

What is the function of packing materials in the joint of concrete pipes in pipe jacking?

Packing materials are about 10mm to 20mm thick and are normally made of plywood, fibreboard or other materials. In case packing materials are absent in pipe joints for pipe jacking, then any deflection in the joints reduces the contact area of the concrete and it leads to spalling of joints due to high stresses induced. With the insertion of packing material inside the pipe joints, the allowable deflection without damaging the joint during the pipe jacking process can be increased.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Which method of pipe jacking is better, pressure balance method or compressed air method?

Pressure balance method normally requires the use of mechanically operated tunnel-boring machine at its cutting head in pipe jacking. Slurry or steel bulkhead is commonly adopted to provide the balance of earth pressure and groundwater in front of the boring machine. Slurry used in balancing earth pressure and ground water pressure is constantly supplied to the face of the cutting wheel through slurry pipes. The excavated materials drop into a crusher for reduction in material size. Later, the debris and spoils will enter the spoil removal chamber near the invert of the shield and will be transported to ground level through slurry discharge pipes. This method of construction is normally adopted in sand and gravel. However, it suffers from the demerit that it is quite difficult to remove large rock boulders during the advancement of the machine. It is quite time-consuming for workers to go inside the relatively small airlock chamber and remove large bounders by hand tools.

Advertisements

The other type of pressure balance technique is called earth pressure balance method which is commonly used in clay and silty soils. It makes use of the principle of maintaining the pressure of excavation chamber the same as the pressure in ground. The excavated materials are transported through screw conveyor to the jacking pit.

Compressed air method in pipe jacking is commonly adopted in locations where groundwater table is high. An air pressure of less than 1 bar is usually maintained to provide the face support and to avoid water ingress. Pressurization and depressurization has to be conducted for workers entering and leaving the pipe-jacked tunnels. In case of porous ground, certain ground treatment like grouting has to be carried out. The removal of boulders by this method is convenient but it has the disadvantages of slow progress and significant noise problem generated by generators and compressors.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

What is the difference between close mode, open mode and mixed mode of trenchless methods?

(i) Close mode
It refers to mechanically operated TBM using bulkhead or slurry to balance earth pressure and groundwater. There is no manual access to the face of excavation.

(ii) Open mode
It refers free air hand-dug tunnel or compressed air handing tunneling with manual access to face of excavation.

Advertisements

(iii) Mixed mode
It is similar to close mode except that it allows access to the face of TBM for manual removal of obstructions.

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Ask a question