What is the purpose of maintaining excess water head during excavation for bored piles?

Excavation of bored piles is usually implemented by a hammer grab. The steel casing will be extended by welding or bolting on additional casing and is installed by hydraulic oscillator.

Water is pumped into the casing during excavation and excess water head is required to be maintained to prevent any ingress of material at the bottom of casing. Moreover, for excavation below pile casing, the provision of excess water head is essential to maintain bore stability.

Advertisements

This question is taken from book named – A Closer Look at Prevailing Civil Engineering Practice – What, Why and How by Vincent T. H. CHU.

Share this post

Kanwarjot Singh

Kanwarjot Singh is the founder of Civil Engineering Portal, a leading civil engineering website which has been awarded as the best online publication by CIDC. He did his BE civil from Thapar University, Patiala and has been working on this website with his team of Civil Engineers.

If you have a query, you can ask a question here.

Leave a Reply

Your email address will not be published. Required fields are marked *

Ask a question