Why do compliance test be carried out some time after the completion of vibrocompaction?

A process called “ageing” occurs after the operation of vibrocompaction. It is observed that sand fill shows an increase in strength and stiffness. Upon immediate completion of vibrocompaction, the apparent increase in strength of sand fill is due to dissipation of air and water pressure. Then the ageing process shall continue owing to creep and cementation.

Hence, sufficient time shall be established for ageing of sand fill to develop prior to compliance testing (such as CPT test). Otherwise, it may result in non-compliant strength and requires re-compaction.

Advertisements

This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

Share this post

Kanwarjot Singh

Kanwarjot Singh is the founder of Civil Engineering Portal, a leading civil engineering website which has been awarded as the best online publication by CIDC. He did his BE civil from Thapar University, Patiala and has been working on this website with his team of Civil Engineers.

If you have a query, you can ask a question here.

Leave a Reply

Your email address will not be published. Required fields are marked *

Ask a question